Schedule
Hardware:
- FY02: design OMs & DAQ/build OMs & test bed
- FY03: deploy 6 strings & test DAQ board, build DAQ
- FY04: deploy 8 strings & install 4800 channel DAQ
- FY05: deploy 16 strings & commission detector
- Ö
- FY??: 14 strings
Software for the Hardware (at Pole)
- FY02: design system/implement infrastructure, exp. control, string control
- FY03: implement trigger, event builder software start taking calibration data on test bed.
- FY04: implement remote calibration & data taking
- FY05: commission the detectorÖ finalize calibration/trigger procedures, monitor the detector stability, & fine tune the operation